Fontainebleau Las Vegas opened to the public shortly before midnight on December 13, 2023. Its blue-glass tower had stood unfinished for years on the north Strip. The opening brought a long-delayed Las Vegas project into operation under a name already associated with the separate Fontainebleau Miami Beach hotel, which opened in 1954.
An unfinished tower
Construction was under way in 2007, but financing troubles interrupted the project. Tutor Perini’s 2009 annual report, describing its plumbing subsidiary’s involvement, records work stopping and the project shutting down by June 2009. The developer entered Chapter 11 that month. A tall, largely built structure did not mean an operating hotel or casino.
The Drew proposal
The same filing describes the January 2010 bankruptcy auction won by an Icahn company. Years later, Witkoff and Marriott announced a different plan: The Drew Las Vegas, with EDITION and JW Marriott hotels. Their February 2018 announcement anticipated a late-2020 debut. It remained a development name and forecast, rather than a casino that welcomed guests under that name.
The return to Fontainebleau
In February 2021, Koch Real Estate Investments announced that it had acquired the unfinished property in partnership with Fontainebleau Development. Jeffrey Soffer’s company returned to the project. A November ceremony marked the renewed push to complete the resort under the Fontainebleau name; it was not the start of all construction on an empty site.
The public opening
The operator’s announcement after the December 2023 celebrations records the first public guests arriving on December 13. The resort combined hotel accommodation, gaming, convention space, restaurants and entertainment within a tall, integrated development beside the Convention Center’s West Hall. The December 14 announcement date should not be mistaken for the public opening date.
The completed resort
The operating resort remains at 2777 South Las Vegas Boulevard in October 2026. Its current presentation includes rooms, dining, entertainment and the Hall of Excellence. These are later chapters in an open resort, distinct from the abandoned opening forecasts of its construction years. The retained historical May 2026 photograph shows the completed lobby and registration area, not the tower exterior or an earlier casino.